A ground-up development pro forma is a projection that runs from land closing to stabilization and sale. It has four parts: a cost budget, a construction and lease-up timeline, a financing plan, and a stabilized operating forecast. The headline output is yield on cost, the stabilized NOI divided by total project cost. If that yield does not beat the exit cap rate by a comfortable margin, the project does not pay for its risk.
This guide builds one on a single 120-unit multifamily project with the arithmetic shown, so you can check it against your own model.
The deal
A developer controls a site for $3,600,000, or $30,000 per unit, and plans 120 apartments. Construction takes 24 months and lease-up takes another 12. The plan is to sell the stabilized property at month 36. A construction lender funds 60% of total cost.
Every figure below is an assumption. In a well-built model each sits in its own labeled blue-font cell, and everything else is a formula.
Step 1: The cost budget
Development budgets are built from land, hard costs, soft costs, contingency, and financing costs.
- Land: $3,600,000.
- Hard costs: $175,000 per unit x 120 = $21,000,000. This is the construction contract.
- Soft costs: 18% of hard costs, covering design, permits, legal, and fees = $3,780,000.
- Contingency: 5% of hard costs = $1,050,000.
Before financing costs, the project costs $3,600,000 + $21,000,000 + $3,780,000 + $1,050,000 = $29,430,000.
Two financing costs remain, and both depend on the loan, which depends on the total. That circularity is the first thing a development model has to handle correctly.
Step 2: Financing and the interest reserve
The loan is 60% of total cost. Equity goes in first, so the lender funds nothing until the equity is spent. Interest accrues at 7.5% on the drawn balance and is capitalized, meaning it is added to the loan rather than paid in cash. The lender also charges a 1% origination fee on the loan.
Solving the circularity gives:
- Interest reserve: $2,174,445, the interest accrued over 36 months.
- Origination fee: 1% of the loan = $190,764.
- Total project cost: $29,430,000 + $2,174,445 + $190,764 = $31,795,210.
- Construction loan: 60% x $31,795,210 = $19,077,126.
- Equity: $31,795,210 - $19,077,126 = $12,718,084.
The interest reserve is 6.8% of total cost. Leave it out, or use a rough guess, and the loan, the equity check, and the return are all wrong. Because equity funds first, the lender’s money is outstanding for a shorter time than a straight-line draw would suggest, which lowers the reserve. If construction slips by six months, the reserve grows and so does the check.
Step 3: The stabilized operating forecast
Stabilized NOI is built the same way as for an existing building. For the full line-by-line method, see what an NOI walk is. This example uses a rent of $2,150 per month.
| Line | Calculation | Annual |
|---|---|---|
| Gross potential rent | 120 x $2,150 x 12 | $3,096,000 |
| Vacancy and credit loss | 6% of GPR | ($185,760) |
| Other income | 120 x $70 x 12 | $100,800 |
| Effective gross income | $3,011,040 | |
| Management fee | 3% of EGI | ($90,331) |
| Operating expenses | 120 x $5,500 | ($660,000) |
| Replacement reserves | 120 x $250 | ($30,000) |
| Net operating income | $2,230,709 |
Use a rent that the market supports today, not a rent you hope to reach after two years of growth. A development model that needs rent growth to work is a bet on the market, not on the project.
Step 4: Yield on cost and the development spread
Yield on cost is stabilized NOI divided by total project cost:
$2,230,709 / $31,795,210 = 7.02%.
Now compare it with the exit cap rate. Assume buyers pay a 5.50% cap rate for new, stabilized product in this market. The development spread is:
7.02% - 5.50% = 152 basis points.
That spread is the reason to build instead of buying. A developer is taking on entitlement, construction, cost, and lease-up risk, and the spread is the pay for it. A thin spread leaves no room for a cost overrun or a slow lease-up. The same logic runs through how to choose an exit cap rate.
Step 5: Exit value and profit
At month 36 the property is stabilized and sells on its NOI.
$2,230,709 / 5.50% = $40,558,342 gross sale price.
Subtract 2% selling costs ($811,167) and repay the construction loan balance of $19,077,126:
$40,558,342 - $811,167 - $19,077,126 = $20,670,049 of net proceeds to equity.
- Profit: $20,670,049 - $12,718,084 = $7,951,965.
- Equity multiple: $20,670,049 / $12,718,084 = 1.63x.
- Profit margin on cost: value of $40,558,342 over cost of $31,795,210 is 1.28x, or a 27.6% margin.
Step 6: IRR
Equity flows are monthly. $3,790,764 goes in at closing for land and the loan fee, then $1,076,250 a month from the construction budget until the $12,718,084 of equity is spent in month 9. The lender funds the rest. No cash comes back until the sale at month 36.
Run on those monthly flows, the levered IRR is 19.4%.
An IRR on a development deal is the part most people misread. The multiple is modest at 1.63x, but the capital is outstanding for an average of well under three years, so the annualized return looks high. Always show IRR and multiple together, as the investment committee will ask for both. See what institutional investors look for.
Step 7: Stress the three things that move
Development returns are most sensitive to the exit cap rate and to construction cost.
| Case | Yield on cost | Levered IRR | Equity multiple |
|---|---|---|---|
| Base case, 5.50% exit cap | 7.02% | 19.4% | 1.63x |
| Exit cap 5.25% | 7.02% | 23.3% | 1.77x |
| Exit cap 5.75% | 7.02% | 15.7% | 1.49x |
| Hard costs +10%, 5.50% exit cap | 6.45% | 12.4% | 1.37x |
A 10% overrun on hard costs, on top of a bigger interest reserve, cuts the yield on cost to 6.45% and the development spread to 95 basis points. The IRR falls by seven points. This is why contingency exists and why a model should let you change one cost line and see the whole chain move.
Common development pro forma mistakes
- Ignoring the interest reserve. It is a cost, it is circular with the loan, and it grows with delay.
- Straight-lining the lease-up. Income arrives late, so the carry is real.
- Underwriting to future rent. Use today’s achievable rent and test growth separately.
- Too little contingency for the stage of design. Early plans need more.
- Hardcoded numbers inside formulas. A reviewer cannot audit what they cannot see.
What a good development model looks like
UnderwritRE is commercial real estate underwriting software that turns guided inputs into institutional-grade, fully dynamic Excel models and investor-ready PDFs. It includes a Development model type. The standard it holds to is the one in this guide: every assumption in a labeled blue-font cell and every other cell a live formula, so a reviewer can trace the return back to a land price, a hard cost, or a cap rate.
For the stabilized-property side of the same work, read the multifamily underwriting guide. To see how the software approaches this, visit real estate pro forma software, CRE financial modeling software, the Learn hub, or the UnderwritRE home page.
Frequently asked questions
What is a development pro forma?
A development pro forma is a projection of a ground-up project from land purchase to sale or refinance. It combines a total cost budget, a construction and lease-up timeline, a financing plan, and a stabilized operating forecast, then reports yield on cost, profit, IRR, and equity multiple.
What is yield on cost and why does it matter?
Yield on cost is stabilized net operating income divided by total project cost. It is the development equivalent of a going-in cap rate. The gap between yield on cost and the exit cap rate, called the development spread, is the margin that pays for construction risk. The required size depends on the market and the lender.
What is an interest reserve in a construction loan?
An interest reserve is a portion of the loan set aside to pay interest during construction and lease-up, when the property produces little or no income. It is a real project cost, so it belongs in the budget and the loan amount, and it grows with the construction timeline.
How much contingency should a development budget carry?
Contingency is commonly set as a percentage of hard costs, often between 3% and 10% depending on how complete the plans are and how much of the contract is fixed price. Earlier-stage plans justify a higher figure. The right number is whatever the project team and lender will defend.